9.11 Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows:
Task                Time               Immediate Processor
A                     12                    –
B                     15                    A
C                     8                      A
D                     5                      B,C
E                      20                    D
 
 
 
Rosenberg’s goal is to produce 180 PDAs per hour.
 a) What is the cycle time?
b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?
c) Can the theoretical minimum actually be reached when workstations are assigned?
 
 9.13 Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows:
 
Task                Time               Immediate Predecessors
A                     10                    –
B                     12                    A
C                     8                      A,B
D                     6                      B,C
E                      6                      C
F                      6                      D,E
 
 
a) What is the theoretical minimum for the smallest number of workstations that Helms can achieve in this assembly line?
b) Graph the assembly line and assign workers to workstations. Can you assign them with the theoretical minimum?
 c) What is the efficiency of your assignment?
 
9.15 The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 10 minutes.
 
 
 
Activity           Activity Description              Immediate Predecessors                   Time  
A                     Attach wheels to tub                           —                                           5
B                     Attach motor to lid                             —                                           1.5
C                     Attach battery pack                            B                                             3
D                     Attach safety cutoff                           C                                             4
E                      Attach filters                                       B                                             3
F                      Attach lid to tub                                 A, E                                         2
G                     Assemble attachments                                    —                                           3
H                     Function test                                       D, F, G                                    3.5
I                       Final inspection                                   H                                             2
J                       Packing                                               I                                               2
 
a) Draw the appropriate precedence diagram for this production line.
b) Assign tasks to workstations and determine how much idle time is present each cycle.
c) Discuss how this balance could be improved to 100%.
d) What is the theoretical minimum number of workstations?
 
 
“WE’VE HAD A GOOD SUCCESS RATE ON THIS ASSIGNMENT. PLACE THIS ORDER OR A SIMILAR ORDER WITH HOMEWORK AIDER AND GET AN AMAZING DISCOUNT”
The post What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line? appeared first on Homeworkaider.


What Students Are Saying About Us

.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐
"Honestly, I was afraid to send my paper to you, but you proved you are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"

.......... Customer ID: 11***| Rating: ⭐⭐⭐⭐⭐
"This company is the best there is. They saved me so many times, I cannot even keep count. Now I recommend it to all my friends, and none of them have complained about it. The writers here are excellent."


"Order a custom Paper on Similar Assignment at essayfount.com! No Plagiarism! Enjoy 20% Discount!"