Assignment – Activities and Project Schedule
You are the project manager for a company website portal (similar to the Modda Customer
Portal, described in the class). You are now detailing the project plan schedule – using the MS
Project Gantt Chart – for the “Register and Search” feature.
To do that, please use the activities, activity durations and the resources, as well as the rest
of the information provided below. You also need to derive the task dependencies.
Note that the activities span multiple SDLC phases: planning, design, development, and
testing.
Hint: for guidance/reference, please feel free to use the Modda POC.mpp example (also
available as a PDF), which i upload the file
Documentation folder
Upon completion, please email the .MPP file to the instructor
Assignment Details: please represent the Gantt chart using the information outlined below.
Project Name: Registration and Search (in the Gantt chart, this should be the parent of all your tasks)
Project Start Date: 10/21/2019
Resources (Note: please observe what tasks each resource may be assigned to):
• 3 Business analysts (BA1, BA2 and BA3) for requirements, low fidelity prototypes and test cases
• 1 UX designer for: review low-fidelity prototypes and develop the high-fidelity prototype (UX1)
• 3 developers / designers for design, build and unit test (Dev1, Dev2 and Dev3)
• 1 Solution Architect (SA1) for design and code review
Tasks / activities:
• Plan Search
o Planning/Requirements
▪ Google-type search requirements
• Identify stakeholders (1 day)
• Conduct requirements meetings (3 days)
• Create low-fidelity prototype (4 days)
• Review and finalize requirements (3 days)
▪ Drill-down search requirements
• Identify stakeholders (1 day)
• Conduct requirements meetings (2 days)
• Create low-fidelity prototype (3 days)
• Review and finalize requirements (4 days)
▪ Content Management (create / edit / remove and publish website content)
• Identify stakeholders (0.5 days)
• Conduct requirement meetings (1 day)
• Create low-fidelity prototype (1.5 days)
▪ Review and finalize all requirements (2 days)
▪ Prototype Requirements
• Review low-fidelity prototypes (1 day)
• Draft high-fidelity prototype (10 days)
• User review and feedback (2 days)
• Finalize high-fidelity prototype (3 days)
▪ Requirements completed (0 days)
o Design and Build
▪ Design
• Design Google-type search (3 days)
• Design drill-down search (2 days)
• Design content management (2 days)
• Review all design (1 day)
• Design approved (0 days)
▪ Coding
• Code Google-type search (15 days)
• Unit test Google-type search (3 days)
• Code drill-down search (10 days)
• Unit test drill-down search (3 days)
• Code content management (7 days)
• Unit test content management (2 days)
• Review all code (5 days)
• Code approved (0 days)
▪ Design and Code Complete (0 days)
o Create Test Cases
▪ Google-search test cases
• Develop Test Case 1 (4 days)
• Develop Test Case 2 (3 days)
▪ Drill-down test cases
• Develop Test Case 3 (3 days)
▪ Content management test cases
• Develop Test Case 4 (2 days)
• Develop Test Case 5 (2 days)
▪ Test Cases completed (0 days)


What Students Are Saying About Us

.......... Customer ID: 12*** | Rating: ⭐⭐⭐⭐⭐
"Honestly, I was afraid to send my paper to you, but you proved you are a trustworthy service. My essay was done in less than a day, and I received a brilliant piece. I didn’t even believe it was my essay at first 🙂 Great job, thank you!"

.......... Customer ID: 11***| Rating: ⭐⭐⭐⭐⭐
"This company is the best there is. They saved me so many times, I cannot even keep count. Now I recommend it to all my friends, and none of them have complained about it. The writers here are excellent."


"Order a custom Paper on Similar Assignment at essayfount.com! No Plagiarism! Enjoy 20% Discount!"